Vietnam is moving closer to opening Long Thanh International Airport, one of the country's largest infrastructure projects. Construction work is progressing quickly, and officials expect the airport to begin commercial operations later this year.

The passenger terminal, which is the airport's main building, has now reached about 70% completion. Contractors are working on the final stages to prepare the terminal for trial operations starting in September.

As construction continues, workers are installing equipment, testing important airport systems, and completing the remaining interior work. These final preparations will help ensure the airport is ready to welcome its first commercial passengers.

Passenger Terminal Nears Completion

The passenger terminal is the most important part of Long Thanh Airport. According to Airports Corporation of Vietnam (ACV), construction work is moving forward as planned.

The main concrete structure, including the basement and four upper floors, has already been completed. Workers have also finished the large steel roof structure.

Construction teams are now focusing on interior work, installing the glass skylight roof, and completing the outdoor landscaping. Their goal is to have the terminal mostly finished before trial operations begin.

Passenger Terminal Progress

70%

Overall Project

About 70% Complete
80%

Civil Construction

Nearly Complete

Main Structure

Completed

Steel Roof Structure

Completed

The steel roof framework and roofing system have been completed, allowing work to continue inside the terminal.

Interior & Landscaping

In Progress

Workers are completing interior finishes, installing the skylight roof, and preparing outdoor areas before trial operations.

Construction Update: The passenger terminal has entered its final construction stage, with attention now focused on interior finishing, equipment installation, and operational readiness.

Airport Equipment Installation Continues

Construction is only one part of the project. The airport also needs modern equipment before it can receive passengers. One of the most important systems is the baggage handling system, which moves passengers' luggage through the airport.

Workers have completed the installation of the main conveyor systems and are now carrying out inspections and functional tests before the equipment becomes operational.

Security equipment, boarding bridges, elevators, escalators, and moving walkways are also being installed across the terminal to prepare the airport for future passenger operations.

Baggage System

Main conveyor systems have been installed and are now being tested.

Security Equipment

Most baggage screening machines have arrived and many are already connected.

Boarding Bridges

Passenger boarding bridges are being connected and prepared for testing.

Passenger Facilities

Escalators, elevators, and moving walkways are being installed.

Airport Infrastructure Is Almost Ready

The airport project includes much more than the passenger terminal. Roads, runways, taxiways, fuel systems, and aircraft parking areas are also being completed.

The first runway is largely finished, while concrete work on the second runway has already been completed. Equipment installation will begin soon.

The fuel supply system has passed 80% completion, while work continues on cargo facilities, airport management systems, and internal roads.

Major Airport Construction Progress

Project Status
Passenger Terminal 70% Complete
Aviation Facilities Nearly 80%
First Runway Mostly Completed
Second Runway Concrete Completed
Fuel Supply System 80%+ Complete
Cargo Terminal No. 1 Under Construction

Trial Operations Will Begin Soon

Before opening to passengers, Long Thanh Airport must complete several rounds of testing between September and November.

Airport staff will test baggage systems, passenger services, security equipment, aircraft handling procedures, and communication systems.

Government agencies will also inspect and certify the airport before commercial flights officially begin.

September

First round of airport system testing.

October

Equipment inspections and operational checks continue.

November

Final testing before commercial passenger operations.

A New Aviation Hub for Vietnam

Long Thanh International Airport is expected to become one of the most important airports in Southeast Asia. The new airport will reduce pressure on Tan Son Nhat International Airport and improve passenger travel.

The airport will strengthen Vietnam's international connections by supporting tourism, trade, and business activities for many years.

As construction enters its final stage, Long Thanh Airport is moving closer to welcoming its first passengers and becoming one of the country's largest aviation centers.

Looking Ahead: Long Thanh International Airport is expected to play a major role in Vietnam's future aviation network while improving travel capacity and reducing congestion at existing airports.

Frequently Asked Questions (FAQ)


The passenger terminal is about 70% complete, while civil construction work is nearly 80% finished.

Trial operations are planned between September and November before commercial services begin.

Workers are completing interior areas, landscaping, equipment installation, and system testing before the airport opens.

The main baggage handling system has been installed, and functional testing is currently taking place before operations begin.

The airport will reduce congestion at Tan Son Nhat Airport and improve Vietnam's international aviation network.

Runways, taxiways, fuel systems, cargo facilities, boarding bridges, elevators, and airport management systems are all progressing toward completion.